Building shell is complete

Post by jordansparks »

The shell of our new 8000 sf building is complete. It's now weatherproof and secure, interior framing is done, and landscaping is done. Progress will continue slowly over the next year or so. It will need heat, electricity, drywall, etc.
jordansparks
Site Admin
Posts: 148
Joined: Thu Aug 27, 2015 3:59 pm

Re: Building shell is complete

Post by jordansparks »

Sprinkler system is installed.
Mati_Roy
Posts: 20
Joined: Fri Jan 11, 2019 5:42 pm

Re: Building shell is complete

Post by Mati_Roy »

I'd be curious to see a picture :)
jordansparks
Site Admin
Posts: 148
Joined: Thu Aug 27, 2015 3:59 pm

Re: Building shell is complete

Post by jordansparks »

Electrical and plumbing rough-in are done. Drywall is underway. The 1500 L microbulk liquid nitrogen (LN2) tank has been ordered and will arrive soon. This tank is 8' tall and 4' in diameter, so it's not huge. We don't go through a lot of LN2, but it's essential that we always have it on hand and that it's reliable. It will be kept full by deliveries from a semitruck about once a month. It's higher pressure than the portable 200 L tanks that we currently get delivered, with a normal evaporation rate (NER) of 1% instead of 2.5%.
jordansparks
Site Admin
Posts: 148
Joined: Thu Aug 27, 2015 3:59 pm

Re: Building shell is complete

Post by jordansparks »

Roof top A/C units were craned into place yesterday.